76,957 power poles to be replaced in Meghalaya, CM says outages are maintenance, not load-shedding

Date:

Share post:

SHILLONG, FEB 23: Chief Minister Conrad K Sangma on Monday announced that more than 76,957 electricity poles will be replaced across Meghalaya under the Revamped Distribution Sector Scheme (RDSS), with outages required for the work.

“The power cuts are not scheduled load-shedding… there are rusted poles, more than 1,000 transformers which are of low capacity and very old in nature. There are wires that have been there for the last 30 years,” Sangma said, replying to the debate on the Governor’s Address.

He explained that supply must be switched off while poles, wires and transformers are changed.

“All these disruptions… are not because of load-shedding but because of the requirement for implementation of the project,” he said.

Sangma added that the department and MeECL will advertise shutdowns in advance and said the drive aims to improve power quality.

Share post:

-->
spot_img

Popular

More like this
Related

Kwah ki Khlieh Nongsynshar ban nang iohbor ban lah iada ia ka mariang ha ri-lum Jaintia

Shillong, Iaiong 10 : Ki Khlieh Nongsynshar na kylleng...

Khur takma ki nongialehkai ka Jylla ha ka Khelo India Tribal Games 2026

Shillong, Iaiong 10: Ki nongialehkai ka Jylla Meghalaya kila...

Assam | Khynra ki Pulit ia ka Iing u President ka AJP | Kynnoh kynshoit ba pynkulmar ha Khowang

Dibrugarh, Iaiong 10: Ka jingïakynad ha ka saiñ hima...